July 10, 2009

Hoku Provides Update to Polysilicon Production Strategy

Filed under: HOKU — Tags: , , , , , , — Jason @ 5:10 pm

Friday July 10, 2009, 5:10 pm EDT

Hoku Materials, Inc., a wholly-owned subsidiary of Hoku Scientific, Inc. (HOKU), established to manufacture and sell polysilicon for the solar market, today announced it is in discussions with several strategic and financial investors regarding debt and equity financing. While the Company reported that the various sources of funding look promising, it expects it will need a few months to work through these options. Hoku also reported that, in addition to seeking debt and equity alternatives, it had retained Deutsche Bank Securities, Inc. as its financial advisor to seek a possible sale of the Company.

To preserve cash and value while pursuing these opportunities, Hoku Materials will begin issuing orders for a temporary slowdown of construction and procurement activity at the polysilicon production facility currently under development in Pocatello, Idaho. The Company had previously announced a strategic delay in constructing the TCS portion of the plant, and now plans to extend the slowdown to temporarily include the other areas as well.

“While we would prefer to progress faster in Pocatello, we remain very encouraged by the strong interest in our project among potential financiers, and by the continued commitment of our vendors and customers, as seen in recent amendments,” said Dustin Shindo, chairman and chief executive officer of Hoku Scientific, Inc. “Despite this temporary slowdown, we remain absolutely confident that this plant will be completed and that we can meet our customer commitments. To that end, we have no plans to lay off any of our staff, including the first group of plant operators that we hired in Pocatello in June.”

“We are caught in the same perfect storm that many other companies are facing: The credit crunch, a general economic downturn, pressure on polysilicon and PV pricing, and a global decline in investment capital,” said Mr. Shindo. “Despite these challenges, we’ve made great progress in construction and we remain well-positioned to complete and operate our plant. Further, we have no senior bank debt on the project, which gives us flexibility in structuring our future plant financing.”

“This type of curtailment is fairly common on projects of this scale and complexity,” said Mason Evans, CEO of J.H. Kelly, Hoku Materials’ General Contractor. “They’ve gotten a few tough breaks with the market and general economic conditions, but having worked closely with Hoku Materials since they broke ground in 2007, we remain very confident that they will resolve the financing challenges and get us back to work quickly. We look forward to completing this facility for them. In the meantime, we are maintaining a full time staff at the Pocatello site to ensure our ability to quickly ramp back up.”

Commenting on Hoku Solar, the Company’s Hawaii-based subsidiary focused on turnkey integration of photovoltaic (PV) power systems, Mr. Shindo noted, “The challenges in funding the polysilicon plant and the temporary construction slowdown applies exclusively to Hoku Materials. The companies are both wholly-owned subsidiaries of Hoku Scientific, but each operates completely independently of the other. We remain very excited about the opportunity to continue expanding Hoku Solar’s PV installation business and continue to actively install systems in Hawaii.”

Advertisements

Leave a Comment »

No comments yet.

RSS feed for comments on this post. TrackBack URI

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Blog at WordPress.com.

%d bloggers like this: